West Basin Redevelopment
Why is the West Basin being redeveloped?
The West Basin redevelopment is intended to strengthen connections between downtown Anacortes and the waterfront while creating new public spaces, improving access, and supporting economic development.
Concepts to redevelop the West Basin date back to 1983 and have evolved through multiple planning efforts, including 2014 North & West Basin Concept Plan and the 2018 Redevelopment Strategy Report. The vision includes improved waterfront access, better pedestrian and bicycle connectivity, enhanced parking, new public spaces, and opportunities for future waterfront-oriented development.
What is included in the redevelopment?
The redevelopment includes a mix of public improvements and future development opportunities designed to enhance the waterfront experience.
Key elements include:
- A new Event Facility
- A waterfront park at the end of Ninth Street
- Improved pedestrian and bicycle connections
- Parking improvements
- Roadway and infrastructure upgrades
- Waterfront esplanade enhancements
- Future development sites for commercial, hospitality, and waterfront-oriented uses
Together, these improvements are intended to create a more connected and active waterfront district.
What benefits will the redevelopment provide to the community?
Improving public access to the waterfront is one of the primary goals of the project. The redevelopment will add a new 16,000-square-foot waterfront park, improve trail and pedestrian connections, increase ADA accessibility, and strengthen links between downtown, the marina, and the shoreline. The project will also create new opportunities for community gathering spaces, local business activity, and year-round waterfront use.
The public waterfront esplanade already stretches nearly a mile between Rotary Park and Seafarers Memorial Park, and the redevelopment continues that long-term investment in shoreline access.
How was the redevelopment plan developed?
The redevelopment plan has been shaped through years of planning, community input, technical analysis, and public review.
Key planning milestones include the 2014 North & West Basin Concept Plan, the 2018 Redevelopment Strategy Report, engineering and environmental studies, public workshops, City review processes, and the approved Framework Development Plan for the West Basin redevelopment area.
The public has had many opportunities to participate in the planning process. Residents, businesses, marina users, City leaders, Port leadership, and community stakeholders have all contributed input along the way.
How does the Event Facility relate to the West Basin redevelopment?
The Event Facility is a key component of the West Basin Redevelopment and was initiated as a joint project between the City of Anacortes and the Port of Anacortes as part of the broader redevelopment effort.
While the West Basin Redevelopment is being led by the Port on Port-owned property, the Event Facility is being developed through a partnership between the City and Port. Under interlocal agreements between the two agencies, the City and Port are working together to develop the facility for which the Port will provide the site. The Port will own and operate the community gathering space on the waterfront once it is opened.
When will redevelopment start, and how long will it take?
The project is currently in the permitting and design phase.
The schedule includes:
- 2022: Feasibility and planning
- 2023-Present: Permitting
- 2026: Final design and bidding
- 2027: Construction
- Spring 2028: Anticipated opening
The redevelopment will be built in phases to help maintain marina operations and public access throughout construction.
How will parking be impacted?
Parking is an important part of the redevelopment plan.
The project will reorganize and enhance parking throughout the West Basin to better serve marina users, visitors, community events, waterfront businesses, and future development.
Parking and transportation studies were completed as part of the planning process, and the redevelopment to help manage parking demand during busy summer periods and special events.
What will happen to the dog park?
The dog park was established as a temporary use of the property and has always been intended as an interim use until redevelopment occurred.
While it is a valued community amenity, it is not the highest and best use of this publicly owned property and redevelopment of the site will require its removal. The City of Anacortes off-leash dog area at Ace of Hearts Rotary Park, located at 38th Street and H Avenue, will continue to be available for dedicated dog park use.
How is the project being funded?
The West Basin Redevelopment and Event Facility are funded separately.
The West Basin Redevelopment is estimated at approximately $10 million and is expected to be funded through a combination of Port funds and grants.
The Event Facility is estimated at approximately $8.4 million and will be funded by the City of Anacortes through lodging tax-supported financing, grants, and other project-specific funding sources.
Will access to the marina and waterfront be impacted?
Temporary impacts may occur during construction, but the project is being phased to help maintain access for marina users and visitors to the waterfront. The Port will share updates and provide advance notice for any upcoming work and impacts to access.
Framework Plan and Shoreline Substantial Development Permit Public Comment Response
SDP and FDP Public Comment Response
2023 West Basin Meetings and Plans
West Basin Binding Site Plan Neighborhood Meeting Recording
Foundation Documents
2008 Comprehensive Plan