T Dock Reconfiguration

Project Location

➢Southwest corner of Cap Sante Marina 

Project Purpose

➢Commercial dock built in 1977, nearing end of useful life
➢Facilitates over $14M annually in commercial activity
➢Supports local Tribal fishing fleet
➢Handles more than 80% of all seafood landed in Anacortes
➢Enlarge & improve dock surface to promote commerce, support local workers, families, and businesses
➢Upsize shore power for future electric vessel needs

Project Outlook

➢2020-2021: Feasibility & Planning
➢2022-Current: Permitting & Design
➢2026: Final Design & Bidding
➢2027-2028: Construction
➢Spring 2028: T Dock Grand Reopening

Project Budget

➢Estimated $10M
➢ $1M funded through WA Department of Commerce
➢ $7.4M funded through US DOT MARAD
➢ $800k funded through EPA Clean Ports