Project Location
⮚ Base of O Avenue, west of Pier 1
Project Purpose
⮚ Pumpout Facility
⮚Vessels prohibited from discharging sewage into Puget Sound, starting in 2024
⮚ Install commercial pumpout facility to support Curtis Wharf users including tugboats, cruise vessels, and fishing vessel Shore-to-Ship Power
⮚ Install mobile shore power system in 2 locations on wharf
⮚ Aid in reducing noise and exhaust pollution while at berth
⮚ Projects combined for both permitting and construction efficiencies
Project Outlook
⮚ 2020: Included in Marine Terminal Modernization Plan
⮚ 2023: Feasibility
⮚ 2024-2025: Design & Permitting
⮚ 2026: Construction
⮚ Fall 2026: Project Complete
Project Budget
⮚ $2.4M
⮚ Pumpout funded by WA Department of Commerce
⮚ Electrification funded by WA Department of Transportation